Timeframe and programme

The project commenced in November 2008 and is expected to finish with a report to the Minister of Education in September 2009.

Timeframe and programme

Details Timeframe
Stage One - Establishment
Project planning and preparation 29 September - 3 October 2008
Stakeholders contacted
Facilitator announced
6 October - 7 November 2008
Working Group meets, is briefed and develops working protocols 7 - 28 November 2008
Stage Two - Participation plan
Working Group develops strategy for first round consultation and wider project 1 December 2008 - 6 February 2009
Stage three - First consultation
Working Group prepares for first round consultation
Community is consulted about high level goals for education
9 February - 27 March 2009
Stage four - Development
Working Group considers community aspirations 30 March - 3 April 2009
Working Group meets fortnightly, develops preferred options and a draft strategy 6 April - 29 May 2009
Stage five - Second consultation
Working Group prepares for second round consultation 1 - 12 June 2009
Preferred options and draft strategy is presented to the community 15 - 26 June 2009
Stage six - Final report
Submissions and feedback analysed and considered by Working Group 29 June - 10 July 2009
Final report prepared 13 - 31 July 2009



Content last updated: 31 July 2009